Update on Sinkhole at Montebello I Water Treatment Plant

Green banner with DPW logo and text "Department of Public Works Press Release"

On Wednesday afternoon, Department of Public Works (DPW) personnel discovered a sinkhole at the Montebello 1 Water Treatment Plant, likely caused by erosion to a stormwater main installed in the 1880s. To ensure the safe mitigation of the sinkhole, DPW has determined that the best course of action is to stop the flow through the exposed 84-inch water main that is currently partially suspended above the sinkhole. This action is out of an abundance of caution and to ensure the safety of those working at the location.

“DPW personnel conducted water system testing, confirming no bacteriological contamination. Due to the 84-inch water main being taken offline, a 48" water main is being activated, and some customers may experience lower than normal water pressure.

“DPW continues to work with our state and local partners to stabilize the site safely. Additionally, DPW is in regular communication with the Maryland Department of Environment.

“DPW and the entire Scott Administration remain committed to keeping residents and businesses informed and will provide regular updates as information becomes available.”

Director Jason W. Mitchell, Ed.D.

Related Stories

Baltimore City Department of Public Works Proposes Multi-Year Rate Adjustments

The Baltimore City Department of Public Works (DPW) has proposed a multi-year rate adjustment to utility rates aimed at maintaining the financial sustainability of the City's aging water and wastewater system. The adjustment will support the necessary capital investments to meet federal and state regulatory standards and meet rising costs driven by inflation.

DPW Offices, Sanitation Yards Closed on Thanksgiving Day, Thursday, Nov. 28

The Baltimore City Department of Public Works (DPW) Director Khalil Zaied reminds residents that all DPW offices and sanitation yards will be CLOSED on Thanksgiving Day, Thursday, November 28, 2024.

DPW Extends Public Comment Period on Modified Consent Decree Revised Operation & Maintenance Plan to December 16

The Modified Consent Decree Revised Operation and Maintenance (O&M) Plan has officially been released by the Baltimore City Department of Public Works (DPW) and is available on the DPW website for review and comment in accordance with the Modified Sanitary Sewer Consent Decree (MCD). DPW has extended the public comment period pertaining to this document for an additional 30 days, through December 16, 2024. Comments may continue to be submitted directly to Michael.Shipman@baltimorecity.gov.