Race Street Project Now Complete

Green banner with DPW logo and text "Department of Public Works Press Release"

BALTIMORE, MD —  Work on the long-awaited Race Street project has been completed, Baltimore City Department of Public Works Director Rudolph S. Chow, P.E., announced today. Repairs were made to a collapsed stormwater line that also undermined and forced the closure of much of this South Baltimore Street for years.

In addition to restoring the century-old storm drain structure, improvements were made to sewer and water infrastructure, including the installation of a 10-inch sanitary line and 6-inch and 10-inch water mains.

The $2.4 million Race Street project began to move forward on November 2014, and consisted of nearly 0.8 acres located along Race Street between W. Cross Street and W. Ostend Street. During the project, Race Street was closed from W. Ostend Street to W. Cross Street, along with the intersection of Race Street & W. West Street.

“The Race Street Project demonstrates the importance of strengthening the City’s stormwater, water, and sewer infrastructure to promote healthier communities and cleaner waterways in the City of Baltimore,” said Director Chow. “Communities have the benefit of knowing that their streets and underground infrastructure are secure and safe.”

The Race Street work included:

  • Replacement of an existing box culvert and placement of new precast box culvert sections.
  • Installation of water meters, house connections, new fire hydrants, and water valves.
  • Removal and replacement of concrete sub-base and roadway asphalt surface.

The restoration of Race Street follows other infrastructure work this year by DPW, including repairs to a section of Moravia Road that had been undermined by an eroding stream bed along Biddison Run, and emergency work to correct a failing stormwater drain under Eager Street at Washington Street.

Related Stories

NOW AVAILABLE: DPW’s 2023 Water Quality Report

Today, the Baltimore City Department of Public Works (DPW) is announcing that its 2023 Water Quality Report is available online. This annual report provides Baltimore City, Baltimore County, and Howard County residents with important information about where the City’s drinking water comes from, what chemicals it contains, and how it meets federal standards for tap water. In this report, DPW highlights our employees who monitor and treat the water from the City’s reservoirs, Loch Raven, Liberty, and Prettyboy, and take steps to safeguard the water throughout the distribution process.

DPW Offices, Sanitation Yards Closed on Independence Day , Thursday, July 4

The Baltimore City Department of Public Works (DPW) Acting Director Khalil Zaied reminds residents that Independence Day will be observed on Thursday, July 4, 2024. As a City-observed holiday, DPW offices and sanitation yards will be CLOSED. The Independence Day closure WILL impact weekly trash and recycling collections. Trash and recycling makeup day is Saturday, July 6, 2024. There will be NO street sweeping during the Independence Day closure.  

DPW Offices, Sanitation Yards Closed on Juneteenth City of Baltimore to Observe Juneteenth, Wednesday, June 19

The Baltimore City Department of Public Works (DPW) Acting Director Khalil Zaied reminds residents that Juneteenth will be observed on Wednesday, June 19, 2024. As a City-observed holiday, DPW offices and sanitation yards will be CLOSEDTrash and recycling collections WILL NOT take place on the Juneteenth holiday closure. The trash and recycling make-up day is Saturday, June 22. There will be NO street sweeping during the Juneteenth closure.