The Back River Wastewater Treatment Plant (Back River) has been in compliance with effluent permit levels for four consecutive months. The extension of the Consent Order and Reimbursement Agreement between the Maryland Department of the Environment (MDE) and the City will allow Maryland Environmental Service (MES) to perform the projects and services necessary to ensure continued compliance at Back River. The collaborative efforts of the Baltimore City Department of Public Works (DPW) and MES have produced improved results for Back River.

“Since the approval of the Consent Order in June, we have made substantial progress toward compliance at Back River, which we can attribute to the tremendous efforts of the 180 DPW employees at Back River alongside staff support from MES,” said Jason W. Mitchell, the Director of DPW. “DPW looks forward to building on the success of this partnership and is optimistic about our path forward.”

The Patapsco Wastewater Treatment Plant (Patapsco) has been in compliance with its bacteria limit since early September. DPW continues to partner with MDE and MES to ensure compliance.

DPW releases bi-weekly updates on compliance progress at the Back River and Patapsco wastewater treatment plants.

Related Stories

DPW Offices and Facilities Close for Good Friday, March 29 Trash, Recycling Pickups to Resume Saturday, March 30

Baltimore City Department of Public Works (DPW) Acting Director Khalil Zaied reminds residents that Good Friday, March 29, 2024, is a City holiday and DPW offices and sanitation yards will be CLOSEDThere will be NO trash or recycling collections on Good Friday. Trash and recycling collections, normally scheduled for Friday, March 29, will be collected on the make-up day, Saturday, March 30.

Mayor Scott to Nominate Khalil Zaied as New Director of the Department of Public Works

Mayor Brandon M. Scott has announced his intent to nominate Khalil Zaied as the new Director of the Department of Public Works (DPW). Zaied, who most recently led the Department of Public Works in Champaign, Illinois, will join DPW on March 18, 2024. Previously, he was a nearly 20 year veteran of Baltimore City Government, serving as Deputy Mayor of Operations and Director of Transportation, among other roles.

Mayor Scott, City Agencies Highlight the Return of Weekly Recycling

On Monday, March 4, Mayor Brandon M. Scott, Department of Public Works Interim Director Richard J. Luna, Department of General Services Director Berke Attila, and Baltimore City Chief Administrative Officer Faith Leach joined city staff and community members to highlight the return of weekly, curbside recycling collections for Baltimore City residents, starting Tuesday, March 5.