2100 blk. Brice St
Friday Jan 21st, 2011
Date: Wed. Jan. 26, 2011 to Wed. Feb. 02, 2011
Time: 7:00 a.m. to 5:00 p.m. (Daily)
Location: 2100 blk. Brice St
Des. of Work: S.C.# 878) – Replacement of 8”sanitary pipe line.
Contact: David A. Driscoll (c) 410-365-8383 – 24/7 Field Office Trailer – Week Days – 7:30 a.m. to 3:30 p.m.
Beginning, on Wednesday, Jan. 26, 2011 to Wednesday, Feb. 02, 2011, a city sub-contractor will perform replacement of 8-inch sanitary sewer line. The water service may need to be temporary turned off to make the repairs.
While we endeavor to do everything we can to make operations run smoothly and with minimum disruptions for you and your neighbors, there are times when that will not be possible due to the nature of our work. We do want to hear from you whether it is a suggestion on how we can improve our work or to acknowledge a successful outcome. Thank you in advance for your patience.