DPW Issues Statement: Continued Compliance at Back River Extension of Consent Order, Reimbursement Agreement

Green banner with DPW logo and text "Department of Public Works Press Release"

The Back River Wastewater Treatment Plant (Back River) has been in compliance with effluent permit levels for four consecutive months. The extension of the Consent Order and Reimbursement Agreement between the Maryland Department of the Environment (MDE) and the City will allow Maryland Environmental Service (MES) to perform the projects and services necessary to ensure continued compliance at Back River. The collaborative efforts of the Baltimore City Department of Public Works (DPW) and MES have produced improved results for Back River.

“Since the approval of the Consent Order in June, we have made substantial progress toward compliance at Back River, which we can attribute to the tremendous efforts of the 180 DPW employees at Back River alongside staff support from MES,” said Jason W. Mitchell, the Director of DPW. “DPW looks forward to building on the success of this partnership and is optimistic about our path forward.”

The Patapsco Wastewater Treatment Plant (Patapsco) has been in compliance with its bacteria limit since early September. DPW continues to partner with MDE and MES to ensure compliance.

DPW releases bi-weekly updates on compliance progress at the Back River and Patapsco wastewater treatment plants.

Related Stories

DPW Offices, Sanitation Yards Closed Memorial Day Holiday, Monday, May 26, 2025

The Baltimore City Department of Public Works (DPW) Director Khalil Zaied reminds residents that Memorial Day will be observed on Monday, May 26, 2025. As a City-observed holiday, DPW offices and sanitation yards will be CLOSED on that day. The Memorial Day closure will NOT impact weekly trash and recycling collections, as Monday is not a regularly scheduled curbside collection day. Mechanical street sweeping will be suspended on the holiday.

DPW Marks Major Milestone for Druid Hill Tank Project: Walking Loop Reopens as the Department’s Work at the Park Nears Completion

The Baltimore City Department of Public Works (DPW) has reopened the walking loop around Druid Lake, signaling the near completion of a historic infrastructure project to enclose and protect one of the City’s major drinking water facilities. The reopening of the loop this spring invites residents back to enjoy one of Baltimore’s most scenic and treasured destinations—the iconic Druid Hill Park, often referred to as the City’s version of Central Park.

DPW to Close Reedbird Residential Recycling Center May 17 to Prepare for Start of Facility Modernization Project

The Baltimore City Department of Public Works (DPW) will close the Residential Recycling Drop-off Center at the Reedbird Sanitation Facility starting Saturday, May 17, 2025, as the City of Baltimore prepares to start a multi-year modernization project at this location.