DPW Issues Statement: Continued Compliance at Back River Extension of Consent Order, Reimbursement Agreement

Green banner with DPW logo and text "Department of Public Works Press Release"

The Back River Wastewater Treatment Plant (Back River) has been in compliance with effluent permit levels for four consecutive months. The extension of the Consent Order and Reimbursement Agreement between the Maryland Department of the Environment (MDE) and the City will allow Maryland Environmental Service (MES) to perform the projects and services necessary to ensure continued compliance at Back River. The collaborative efforts of the Baltimore City Department of Public Works (DPW) and MES have produced improved results for Back River.

“Since the approval of the Consent Order in June, we have made substantial progress toward compliance at Back River, which we can attribute to the tremendous efforts of the 180 DPW employees at Back River alongside staff support from MES,” said Jason W. Mitchell, the Director of DPW. “DPW looks forward to building on the success of this partnership and is optimistic about our path forward.”

The Patapsco Wastewater Treatment Plant (Patapsco) has been in compliance with its bacteria limit since early September. DPW continues to partner with MDE and MES to ensure compliance.

DPW releases bi-weekly updates on compliance progress at the Back River and Patapsco wastewater treatment plants.

Related Stories

Baltimore City Department of Public Works Proposes Multi-Year Rate Adjustments

The Baltimore City Department of Public Works (DPW) has proposed a multi-year rate adjustment to utility rates aimed at maintaining the financial sustainability of the City's aging water and wastewater system. The adjustment will support the necessary capital investments to meet federal and state regulatory standards and meet rising costs driven by inflation.

DPW Offices, Sanitation Yards Closed on Thanksgiving Day, Thursday, Nov. 28

The Baltimore City Department of Public Works (DPW) Director Khalil Zaied reminds residents that all DPW offices and sanitation yards will be CLOSED on Thanksgiving Day, Thursday, November 28, 2024.

DPW Extends Public Comment Period on Modified Consent Decree Revised Operation & Maintenance Plan to December 16

The Modified Consent Decree Revised Operation and Maintenance (O&M) Plan has officially been released by the Baltimore City Department of Public Works (DPW) and is available on the DPW website for review and comment in accordance with the Modified Sanitary Sewer Consent Decree (MCD). DPW has extended the public comment period pertaining to this document for an additional 30 days, through December 16, 2024. Comments may continue to be submitted directly to Michael.Shipman@baltimorecity.gov.